Tag Archives: Sheetrock
San Ramon Project is Complete!!!
2/24 – Completion of San Ramon Project. Scope of Work Included: Remodeling the Master Bedroom & Bathroom, Laundry Room, Powder Bathroom, Dining Room Arbor, Kitchen Double Soffit, Family Room & Great Room. Adding a Whole New 2nd Story to the Home Which Included an Office, 4th Bedroom and Full Bathroom. Read More
Drywall & New Fireplaces Installed
1/05- New Fireplaces are Installed in the Living Room and Family Room, Arched Dinning Room Arbor with Soffit and Kitchen Soffit Completed, and Drywall is Almost Complete!
Follow the work in progress! Go to Next Weeks Blog Installation & Details Read More
Getting Close!
12/20 – Exterior Painting & Sheetrock are Complete, Mortar for Tile in Bathrooms is Laid, Stack Stone on Fireplace Hearth is Started, Upstairs Deck is Complete, & Driveway is Ready for Decomposed Granite.
Follow the work in progress! Go to Next Weeks Blog Interior Painting Begins & Tile Work is Almost Complete Read More
EcoSeal, Insulation & Sheetrock
11/22 – 11/28 EcoSeal is Applied (EcoSeal is a sealant that forms an effective and continuous air barrier in the spaces and openings of your building envelope), Insulation Installed, and Sheetrock Hung.
Follow the work in progress! Go to Exterior Painting Begins & the Start of the Driveway Blog Next Week Read More
Windows, Plumbing, Electrical, Sheetrock and Priming
4/5- Windows!
4/12- Roofing, Tyvek, Plumbing
4/19- Electrical going in, Tub set
4/20- Sheetrock
4/27- Paint Priming
Follow the work in progress! Go to Exterior Painting Begins Blog Next
Read More