San Ramon Project is Complete!!!
2/24 – Completion of San Ramon Project. Scope of Work Included: Remodeling the Master Bedroom & Bathroom, Laundry Room, Powder Bathroom, Dining Room Arbor, Kitchen Double Soffit, Family Room & Great Room. Adding a Whole New 2nd Story to the Home Which Included an Office, 4th Bedroom and Full Bathroom. Read More
Interior Painting Begins & Tile Work is Almost Complete
1/5 – Interior Painting Begins, Tile Work is Almost Complete & The Ditch for the Electrical is Dug.
Follow the work in progress! Go to Next Weeks Blog Main House Completed!! Read More
Exterior Painting Begins & the Start of the Driveway
12/05 – 12/13 Exterior Painting Begins, the Start of the Driveway, All Cabinets are Installed, and the Deck is Finished.
Follow the work in progress! Go to Getting Close! Next Weeks Blog Read More
Windows, Plumbing, Electrical, Sheetrock and Priming
4/5- Windows!
4/12- Roofing, Tyvek, Plumbing
4/19- Electrical going in, Tub set
4/20- Sheetrock
4/27- Paint Priming
Follow the work in progress! Go to Exterior Painting Begins Blog Next